With the Future Homes Standard (FHS) due to come into force in March 2027, developers are facing an uncomfortable reality; planning consent alone, may no longer be enough to protect schemes from costly redesigns.
The new standard is set to reduce carbon emissions by 75% compared to 2013 regulations, but with Building Safety Regulator (BSR) reviews stretching form the intended 12 weeks to as much as 50 weeks, projects are increasingly becoming trapped between planning approval, sign-off processes and evolving compliance requirements.
According to Craig Robertson, director at Wallace Whittle, the consequences could be significant. Many stalled projects are unlikely to meet transition deadlines and may require substantial redesigns before reaching site, at a time when the Future Homes Standard is already expected to add £5,000-£10,000 per home and MEP costs have risen by around 30% amid construction inflation and post-Grenfell fire safety requirements.
Drawing on his experience supporting major redevelopment projects, including the 3000-home Elephant Park regeneration scheme in London, Craig can provide expert insight on:
-
Why planning approval alone may not protect schemes from FHS requirements
-
The growing cost and programme risk facing schemes delayed by BSR approvals
-
Whether overheating could become housing’s next major challenge, much as damp and mould have become today
-
What happens when MEP requirements are treated as a late stage add on
-
Why developers need to look beyond minimum compliance and anticipate future regulatory changes
At a time when the industry is balancing housing demand, building safety requirements and net-zero ambitions, Craig can offer practical advice on future proofing residential developments and avoiding costly surprises later in the project lifecycle.